Current Status of Upper Kotmale Hydropower Project.

 

Progress of Upper Kotmale Hydropower Project as of end of March 2012

 

Overall Progress of Upper Kotmale Hydro Power Project

 

 

 

 

Item

Description

% Completed

Lot 1

Preparatory works

94

Lot 2

Main Civil Works

96

Lot 3

Hydro Mechanical Works

100

Lot 4

Electro Mechanical Works

95

Lot 5

Transmission Line

100

 

Overall Progress of the Project:

96

 

 

 

Lot 1

Preparatory works

 

Item

Description

% Completed

1

B – 412 Road & Access roads

100

2

Permanent Facilities for Resettles

 

 

Talawakelle

88

 

Devsiripura & Kumaragama

76

 

Rathnilakelle

100

 

Nanu Oya

100

 

Middleton Division

100

 

CGR Quarters

100

 

UC Resettlement

81

 

Common Buildings

59

3

Permanent Facilities for Employers & Engineer

 

 

Arussella Camp

100

 

Walkers Camp

45

4

33kV Transmission Line

100

 

Overall Progress of Lot 1:

94

 

 

 

Lot 2

Main Civil Works

 

Item

Description

% Completed

0

Site installation and services

83

1

Intake dam

98

2

Head pond area

91

3

Headrace tunnel

98

4

Upstream surge tank

94

5

Penstock

98

6

Powerhouse complex

100

7

Tailrace

100

8

Outdoor switchyard

90

9

Architectural works

92

 

Overall Progress of Lot 2:

96

 

 

 

Lot 3

Hydro Mechanical Works

 

Item

Description

% Completed

1

Spillway Gates

100

2

Spillway Stop log

100

3

Sand Flush Gate

100

4

Stop log Sand Flush

100

5

Main Dam Outlet

100

6

Main Dam Intake

100

7

Trash rack & Raking m/c

100

8

Guide Frame for Intake

100

9

Access door & Drain

100

10

Steel Penstock & Lining

100

11

Draft Tube Gate

100

12

Tail race Gate

100

13

Controls & Power supply

100

 

Overall Progress of Lot 3:

100

 

 

 

Lot 4

Electro Mechanical Works

 

Item

Description

% Completed

1

Turbine

97

2

Generator

98

3

Overhead Travelling Crane

100

4

Power Transformer

98

5

Switchyard Equipment

98

6

Power Plant Equipment

96

7

220kV Cable

98

8

Telecommunication equipment and flood forecasting system

79

9

Miscellaneous Equipment

55

10

Intake Dam equipment

84

11

Expansion of Kotmale Switchyard

98

12

Nuwaraeliya grid station

83

 

Overall Progress of Lot 4:

95

 

 

 

Lot 5

Transmission Line

 

Item

Description

% Completed

1

Design

100

2

Procurement

100

3

Construction

100

 

Overall Progress of Lot 5:

100


Payments:  

No. Service / Contract Local Currency Portion  / LKR Foreign Currency Portion / JPY
Contract value Payment  made % Contract value Payment  made %
1 Consultancy Service 661,249,442.00 582,665,883.55 88.12 2,016,870,146 1,977,718,283 98.06
2 Lot 1 6,328,065,103.64 5,613,175,431.53 88.70 696,529,770 628,823,411 90.28
3 Lot 2 5,609,469,420.81 4,598,006,655.75 81.97 7,726,025,277 6,357,044,795 82.28
4 Lot 3 788,530,330.00 734,121,744.00 93.10 2,060,279,890 1,870,394,890 90.78
5 Lot 4 585,022,787.00 374,549,868.34 64.02 7,972,548,380 6,331,175,079 79.41
6 Lot 5 723,412,519.24 590,130,791.97 81.58 737,846,630 593,457,646 80.43
  Total 14,695,749,602.69 12,492,650,375.14 85.01 21,210,100,093 17,758,614,104 83.73

 

 

 