Current Status of Upper
Kotmale Hydropower Project.
Progress of Upper Kotmale
Hydropower Project as of end of March 2012
|
Overall Progress of Upper
Kotmale Hydro Power Project
|
|
|
|
|
|
|
Item
|
Description
|
% Completed
|
|
Lot 1
|
Preparatory works
|
94
|
|
Lot 2
|
Main Civil Works
|
96
|
|
Lot 3
|
Hydro Mechanical Works
|
100
|
|
Lot 4
|
Electro Mechanical Works
|
95
|
|
Lot 5
|
Transmission Line
|
100
|
|
|
Overall Progress of the Project:
|
96
|
|
|
|
|
|
Lot 1
|
Preparatory works
|
|
|
Item
|
Description
|
% Completed
|
|
1
|
B – 412 Road & Access roads
|
100
|
|
2
|
Permanent Facilities for Resettles
|
|
|
|
Talawakelle
|
88
|
|
|
Devsiripura & Kumaragama
|
76
|
|
|
Rathnilakelle
|
100
|
|
|
Nanu Oya
|
100
|
|
|
Middleton Division
|
100
|
|
|
CGR Quarters
|
100
|
|
|
UC Resettlement
|
81
|
|
|
Common Buildings
|
59
|
|
3
|
Permanent Facilities for Employers & Engineer
|
|
|
|
Arussella Camp
|
100
|
|
|
Walkers Camp
|
45
|
|
4
|
33kV Transmission Line
|
100
|
|
|
Overall Progress of Lot 1:
|
94
|
|
|
|
|
|
Lot 2
|
Main Civil Works
|
|
|
Item
|
Description
|
% Completed
|
|
0
|
Site installation and services
|
83
|
|
1
|
Intake dam
|
98
|
|
2
|
Head pond area
|
91
|
|
3
|
Headrace tunnel
|
98
|
|
4
|
Upstream surge tank
|
94
|
|
5
|
Penstock
|
98
|
|
6
|
Powerhouse complex
|
100
|
|
7
|
Tailrace
|
100
|
|
8
|
Outdoor switchyard
|
90
|
|
9
|
Architectural works
|
92
|
|
|
Overall Progress of Lot 2:
|
96
|
|
|
|
|
|
Lot 3
|
Hydro Mechanical Works
|
|
|
Item
|
Description
|
% Completed
|
|
1
|
Spillway Gates
|
100
|
|
2
|
Spillway Stop log
|
100
|
|
3
|
Sand Flush Gate
|
100
|
|
4
|
Stop log Sand Flush
|
100
|
|
5
|
Main Dam Outlet
|
100
|
|
6
|
Main Dam Intake
|
100
|
|
7
|
Trash rack & Raking m/c
|
100
|
|
8
|
Guide Frame for Intake
|
100
|
|
9
|
Access door & Drain
|
100
|
|
10
|
Steel Penstock & Lining
|
100
|
|
11
|
Draft Tube Gate
|
100
|
|
12
|
Tail race Gate
|
100
|
|
13
|
Controls & Power supply
|
100
|
|
|
Overall Progress of Lot 3:
|
100
|
|
|
|
|
|
Lot 4
|
Electro Mechanical Works
|
|
|
Item
|
Description
|
% Completed
|
|
1
|
Turbine
|
97
|
|
2
|
Generator
|
98
|
|
3
|
Overhead Travelling Crane
|
100
|
|
4
|
Power Transformer
|
98
|
|
5
|
Switchyard Equipment
|
98
|
|
6
|
Power Plant Equipment
|
96
|
|
7
|
220kV Cable
|
98
|
|
8
|
Telecommunication equipment and flood forecasting
system
|
79
|
|
9
|
Miscellaneous Equipment
|
55
|
|
10
|
Intake Dam equipment
|
84
|
|
11
|
Expansion of Kotmale Switchyard
|
98
|
|
12
|
Nuwaraeliya grid station
|
83
|
|
|
Overall Progress of Lot 4:
|
95
|
|
|
|
|
|
Lot 5
|
Transmission Line
|
|
|
Item
|
Description
|
% Completed
|
|
1
|
Design
|
100
|
|
2
|
Procurement
|
100
|
|
3
|
Construction
|
100
|
|
|
Overall Progress of Lot 5:
|
100
|
Payments:
|
No. |
Service /
Contract |
Local Currency Portion /
LKR |
Foreign Currency Portion / JPY |
| Contract
value |
Payment
made |
% |
Contract
value |
Payment
made |
% |
|
1 |
Consultancy
Service |
661,249,442.00 |
582,665,883.55 |
88.12 |
2,016,870,146 |
1,977,718,283 |
98.06 |
|
2 |
Lot 1 |
6,328,065,103.64 |
5,613,175,431.53 |
88.70 |
696,529,770 |
628,823,411 |
90.28 |
|
3 |
Lot 2 |
5,609,469,420.81 |
4,598,006,655.75 |
81.97 |
7,726,025,277 |
6,357,044,795 |
82.28 |
|
4 |
Lot 3 |
788,530,330.00 |
734,121,744.00 |
93.10 |
2,060,279,890 |
1,870,394,890 |
90.78 |
|
5 |
Lot 4 |
585,022,787.00 |
374,549,868.34 |
64.02 |
7,972,548,380 |
6,331,175,079 |
79.41 |
|
6 |
Lot 5 |
723,412,519.24 |
590,130,791.97 |
81.58 |
737,846,630 |
593,457,646 |
80.43 |
| |
Total |
14,695,749,602.69 |
12,492,650,375.14 |
85.01 |
21,210,100,093 |
17,758,614,104 |
83.73 |
|
|