      Key Milestones
 
 Project History
 Project Description
 Need for the Project
 Current Status
 Key Milestones
 Funding


Key Mile Stones Achieved
1 1967 - 1968 Mahaweli MasterPlan identified Upper Kotmale Hydro Power Potential , UNDP  FAO Study
2 1985 - 1987 Feasibility stidies of Upper Kotmale , JICA Grant
3 1993 - 1995 Engineering Service study , Environmental Impact Study of Upper Kotmale Hydro Power Project, OECF Loan
4 1995 - 1998 Studies of alternatives done and appeal for Environmental Clearance.
5 1998 July Environmental Clearance Granted under the National Environmental Act.
6 2000 March The final Environmental Clearance granted subsequent to a settlement of an appeal made in the Court of Appeal by an Environmental NGO.
7 2002 March 13 Cabinet of Ministers approved the loan to finance the UKHP Project.
8 2002 March 28 Loan agreement between the Governments of Japan and Sri Lanka was signed.
9 2002 July 10 Report of the Inter-Ministerial Committee: Upper Kotmale Hydro Power Project. Submitted its report to the government recommending the implementation of the Project with recommendations to mitigate the environmental impacts.
10 2002 August 21 Cabinet of Ministers approved the project with the environmental Mitigation Measures to be published under the National Environmental Act.
11 2003 April 10 Publication of the Gazette Extraordinary bearing number 1283/19 - National Environmental (Upper Kotmale Hydro Hydro-power Project - Monitoring) Regulations No.1 of 2003.
12 2003 October 15 Cabinet of Ministers approved the appointment of Consultants for the implementation of the project.
13 2003 November 5 Consultants were appointed to the project, they commenced the work on November 16, 2003.
14 2004 July 21 Approval of the Cabinet of Ministers for the Strategic Plan to Strengthen the Ceylon Electricity Board ? in which the Implementation of UKHp was given priority.
15 2005 April 07 Cabinet of ministers has taken a decision to proceed with the project limiting it's scope only on st.Clairs waterfall.
16 2005 July 15 Lot-1 Preparatory works contract was awarded to M/S Maeda Corporation of Japan
17 2005 July 27 Lot-1 Contract Agreement was signed between the Ceylon Electricity Board and M/S Maeda Corporation.
18 2006 December 06 Lot-2 Contract Agreement was signed between the Ceylon Electricity Board and M/S Maeda Nishimatsu Joint Venture (MNJV) , Japan
19 2007 November 21 

Lot-3 Contract agreement was signed between Ceylon Electricity Board and M/S Kurimoto LTD, Japan.

20 2008 June 20 Lot-4 Contract agreement was signed between Ceylon Electricity Board and M/S Mitsubishi Corporation, Japan.
21 2009 October 06 Lot-5 Contract agreement was signed between Ceylon Electricity Board and M/S Kinden Corporation, Japan.
22 2010 August 17 Tunnel excavation was completed.
23 2011 November 30 Water filling to tailrace.
24 2011 December 15 Head pond impounding.
 
 