|
The Upper Kotmale Hydropower Project will be implemented through five separate contracts comprising of Lots 1 to 5. Lot 3 Contract, Hydro mechanical Equipment, of Upper Kotmale Hydropower Project is scheduled to be contracted according to the International Competitive Bidding (ICB) turnkey contract. But shall be limited to the Japanese contractors, according to the loan agreement with JBIC, to Design, Supply, Erection and Commission the list of equipment mentioned under the Scope of Work and accounts for about 6.4% of the total project cost.
Lot 3- Scope of Works:
Main Dam and Intake at Talawekele
1. Five (5) sets of Spillway Radial Gates and Hoists
(one with a auxiliary flap on the top) for 10m wide by 12m high dam openings
to control the flood and to maintain the reservoir water level at 1194 msl.
2. One (1) set of Stoplog
for a 10m wide by 12m high dam opening for the maintenance of above Gates.
3. One (1) set of Sand Flushing
Radial Gate and stoplog
with Hoist for a 5.5m wide by 5.5m high opening for sediment discharge
and a stoplog for this.
4. One (1) set of Fixed Wheel Intake Gate and stoplog
with a Hoist for a 4.5m wide by 8.8m high Tunnel opening at the entrance
of the Headrace Tunnel.
5. Three (3) sets of Trashracks
for each of 6.5m wide by 10m high openings and one (1) set of Raking and
Grabbing Equipment for the cleaning and removing of trash, debris and
logs trapped in front of the water entrance to the tunnel.
6. All associated Electrical,
Hydraulic and Control equipment for above.
Diversion Waterway and Power Station
The penstock is located at the end of the tunnel and is facilitated to
direct the water into the Power station. This consists of:
1. One (1) lane Embedded Tunnel Steel Liner of 4.300
m in diameter by 100.00 m in length with One (1) Tee (T) branch and Surge
Tank Steel Liner of 12.0m in diameter by 44.0m in height and One lane
Tunnel Drain Pipeline of 1.5m diameter by 10.0m in length
2. One (1) lane Embedded Steel Penstock
of 4.300 to 3.200 m in diameter by 729.29m in length with one (1) Y type
Bifurcator and two (2) lanes of Branch Pipes 2.1m to 1.45m in diameter
by 36.06m in each branch length
3. Two (2) sets of vertical lift
slide type Draft Tube Gates each of 2.5m span by 3.0m height in the Draft
Tube, with Hoisting Equipment
4. One (1) set of Tailrace
Stoplog of 4.0m span by 4.5m height at the end of the Tailrace Tunnel.
Discharge Facility for St. Clair’s
Water Fall
Unlike in other Hydropower Power projects implemented in Sri Lanka, very
special attention was made to maintain the water release requirement for
the St. Clair’s Water Fall, as it was ordered by Government
Extraordinary
1. St. Clair Falls. – In order
to maintain a continuous flow over the waterfall, a total volume of 47,250m
of water shall be released, per day, for ten (10) half hour periods, daily
between sunrise and sunset
Therefore to accommodate above requirement following equipment shall be
installed:
For St. Clair’s
One (1) lane of steel conduit of 1.2m to 0.8m in diameter by 48.00m approximate
length , One (1) set of Guard Gate and Control Jet flow gate both of 800mm
in Diameter.
All associated Electrical, Hydraulic and Control
equipment for above.
Construction and Procurement schedule
The contract period spans approximately
for a period of 45 months (3yrs and 9 months). It is expected that the
Lot 3 works would commence by mid of 2007 and complete in the first quarter
of 2011.
|