Introduction:
The Upper Kotmale Hydropower Project will be
implemented through five separate contracts named as Lot 1 to 5.
The Lot 5 Contract is to construct the Transmission Line to connect
the UKHP plant to the 220 kV National Grid at the existing Kotmale
substation. The scope of work at Kotmale substation was transferred
to Lot 4 for better contract administration.
Lot 5 - Scope of Works:
Transmission Line
The work includes the supply and erection of
the 220 kV transmission line (18 km long) including foundations
of towers from Upper Kotmale Power House to Kotmale Switchyard.
Shifting of First three spans of existing
Biyagama line
The work includes supply and erection
of 04 nos. 220 kV transmission line towers including foundations
of towers and shifting of first three spans of existing Biyagama
line to new towers.
Construction and Procurement schedule
The contract period is approximately
24 months. It is expected that the Lot 5 works to commence by the
mid of 2007 and to complete in the last quarter of 2009.
|